What a Curtain Wall Client Must Prepare: Project Case Studies from West African Clients
Curtain Walls & Facades › Project case study
A curtain wall project is not started by a drawing set. It is started by eight client decisions: the geometry and panelization, the structural interface, the performance brief, the glass and shading strategy, the movement and tolerance strategy, the mock-up and testing plan, the logistics and installation sequence, and the approval and handover process. This curved facade in West Africa shows why: the APD joinery package fixed the window and door types, but the curved glass bay needed its own system, anchors, panelization, mock-up and site sequence before fabrication.
The project in one view
The building is a five-storey mixed-use project in West Africa: basement parking, ground-floor retail, offices and residences above. The structure is a concrete frame. The facade package combines aluminum windows and doors, balcony glazing, and a curved glass curtain wall at the entrance corner.

The concrete frame before the facade: the slabs, columns and balcony edges set the real tolerances the curtain wall has to absorb.

The side elevation shows the stepped slabs and the curved corner — the two conditions that drove the panelization.
The climate is hot, dusty and seasonal-rain. The system is imported, the site is urban and tight, and the installation is sequenced around scaffolding and limited laydown. Those conditions matter as much as the U-value.

The curved glass bay after installation: a separate engineered system, not a repeated window type.
1. Geometry and panelization
The curved bay is the first thing a drawing set does not fully answer. A plan gives the radius and the chord; it does not give the panel widths, the transom heights, the joint layout or the maximum glass curvature that the selected supplier can produce.
On this project, the curve had to be divided into vertical panels that could be bent, framed, packed and installed without opening a joint beyond the allowable gap. The panelization had to respect:
- the architectural radius and the visible joint rhythm;
- the glass supplier’s minimum and maximum curvature;
- the frame system’s ability to follow the curve without faceting;
- the slab edge and the anchor zone at each level;
- the lifting and handling limits on site.
What the client must provide: the architectural geometry, a measured survey or point cloud, the acceptable joint width, the panel size limits and the glass curvature limits. If the design is still at APD stage, the client should confirm who owns the final panelization — the architect, the facade contractor, or the supplier.
Lesson: a curved facade is not a window type. It is a separate system with its own geometry, engineering and mock-up.
2. Structural interface
The concrete frame is never exactly the drawing. On this project, the exposed slabs, columns and balcony edges showed the usual construction tolerances: slight variations in slab level, column position and edge line. The curtain wall has to absorb those variations without transferring them to the glass.
The interface package must define:
- the slab edge and the anchor zone at each floor;
- cast-in embeds or post-fixed anchors, and who supplies them;
- the concrete strength and edge distance;
- the inter-story drift and slab deflection;
- the movement joint locations and the acceptable gap;
- the waterproofing and flashing interface at the head and sill.
What the client must provide: structural drawings, the specified concrete tolerance, the anchor substrate, the movement data and the waterproofing detail. A measured survey before fabrication is not optional on a curved bay.
Lesson: the frame tolerance is the hidden cost. It is cheaper to survey and adjust the panelization than to rework glass on site.
3. Performance brief
“To code” is not a performance brief. For this climate, the facade has to handle solar gain, dust, driving rain and thermal movement. The performance brief should state:
- design pressure and water penetration resistance;
- air leakage and dust infiltration limits;
- U-value and SHGC targets, and how they are calculated;
- acoustic requirement, if the building faces a road;
- fire performance at the slab edge, if required;
- maintenance and cleaning access.
What the client must provide: the project performance specification, the local code reference and the design pressure. If the client only has an architectural brief, the facade contractor should issue a performance proposal for approval before pricing.
Lesson: in a hot, dusty climate, solar control, drainage and dust sealing matter more than a headline U-value.
4. Glass and shading
The curved glass is a long-lead item. The selection affects the curvature limit, the coating, the colour, the thermal stress and the spare-panel strategy.
The client must decide:
- the glass make-up: double or triple, Low-E, laminated, spandrel;
- the curvature and the visible distortion limit;
- the coating and the reflected colour;
- the spandrel treatment and the visible transmittance;
- the spare panels and the replacement lead time.
What the client must provide: the glass specification, the performance targets, the visual mock-up approval and the spare-panel quantity. On a curved facade, the mock-up should include a curved panel, not only a flat one.
Lesson: order curved glass after the mock-up is approved, not before. A coating or curvature change after fabrication is a full re-order.
5. Movement and tolerances
A curtain wall is a moving assembly attached to a moving structure. The design must define:
- inter-story drift;
- thermal expansion of the aluminum;
- concrete creep and shrinkage;
- seismic movement, where applicable;
- the movement joints and their covers;
- the installation tolerance and the adjustment range.
What the client must provide: the structural movement data, the joint locations and the acceptable visual gap. If the structure is existing, a survey and a movement assessment are needed.
Lesson: movement joints are a design decision, not a site fix. A joint that is too small will crack the sealant or the glass.
6. Mock-up and testing
A project-specific mock-up is the cheapest way to find the interface problems before the facade is fabricated. It should test:
- air leakage (ASTM E283);
- water penetration (ASTM E547, and AAMA 501.2 in the field);
- structural performance (ASTM E330);
- the anchor and the movement joint;
- the curved panel and the corner condition.
What the client must provide: the mock-up location, the test sequence, the acceptance criteria and the sign-off authority. On an overseas project, allow time for the mock-up to be shipped, installed and inspected.
Lesson: a mock-up is not a formality. It is the point where the drawing, the frame and the glass meet.
7. Logistics and installation
On an imported project, logistics is part of the design. The facade must be packed in the installation sequence, shipped without damaging the curved panels, stored without distortion, and lifted without overstressing the frame.
The client must provide:
- site access and laydown space;
- crane or hoist availability and lifting windows;
- scaffolding or mast-climbing access;
- power, water and security;
- storage conditions for glass and aluminum;
- the installation sequence and the temporary seal plan.
What the client must provide: a site logistics plan, the installation programme and the interface with the main contractor. The facade contractor should pack by floor and by elevation, not by profile type.
Lesson: a perfect drawing set can still fail on site if the panels arrive in the wrong sequence.
8. Approvals, shop drawings and handover
The APD set is a design-coordination document. Before fabrication, the project needs:
- execution (EXE) drawings by elevation and by grid;
- head, jamb, sill, mullion and anchor sections;
- structural calculations and movement analysis;
- glass, hardware and finish schedules;
- RFI closure and client sign-off;
- O&M manuals, spare parts and warranty terms.
What the client must provide: the approval authority, the review turnaround, the handover requirements and the warranty expectations. Approvals are on the critical path; a late comment can stop fabrication.
Lesson: the client’s approval process is part of the programme, not an administrative afterthought.
What the APD set did and did not answer
The APD joinery package was useful. It gave the locations, the types, the sizes, the counts and the opening direction. It was fit for design coordination.

The APD location plan fixed where each window and door sits. It did not engineer the curved curtain wall.
It did not answer the curved curtain wall grid, the panelization, the anchors, the movement joints, the glass build-up, the performance values, the mock-up or the installation sequence. That is not a contradiction. It is the normal boundary between an APD set and an EXE package.
Five lessons from the project
- Separate the curtain wall scope from the joinery scope. A window schedule is not a curtain wall package.
- Survey the concrete frame before fabrication. The curved bay has to fit what is built, not what is drawn.
- Design for dust, rain and heat. Solar control, drainage and sealing drive the details.
- Put the mock-up and logistics on the critical path. They are not secondary to the shop drawings.
- Get client decisions before fabrication. Curvature, coating, mock-up and movement joints cannot wait for site.
The client checklist
Before a curtain wall project moves to fabrication, the client should be able to answer these twelve items:
- Architectural geometry and a measured survey.
- Structural drawings, tolerances and anchor substrate.
- Design pressure, air/water, thermal, acoustic and fire requirements.
- Glass make-up, curvature, coating and spandrel.
- Movement data and joint locations.
- Anchor type and edge distance.
- Mock-up location, tests and acceptance criteria.
- Site access, laydown, crane and scaffolding.
- Installation sequence and temporary seals.
- Approval authority and review turnaround.
- O&M, spares and warranty.
- Incoterm, packing and delivery schedule.
If more than three are missing, the project is still at feasibility stage — not at fabrication.
Print it, mark what you already have, and send the gaps with your drawings, schedule and site photos.
Frequently asked questions
What information should a client provide for a curtain wall project?
The eight inputs above: geometry, structure, performance, glass, movement, mock-up, logistics and approvals. A drawing set alone is not enough; the client also needs to confirm who owns the panelization and the interface design.
Why is a curved curtain wall different from a standard window?
A standard window is a repeated product in a rectangular opening. A curved curtain wall is a project-specific system: the panels, frames, anchors and joints are engineered around the radius and the slab edge, and the glass curvature is a supplier limit.
What is the biggest risk in an overseas curtain wall project?
The interface between the imported system and the local structure. Frame tolerance, anchor substrate, movement and installation sequence are the usual failure points — not the glass itself.
Do I need a mock-up?
Yes, for a project-specific or curved facade. The mock-up tests the interface, the drainage, the anchors and the visual quality before the full order is fabricated.
How long does a curtain wall project take?
It depends on the design approval, the mock-up, the glass lead time and the shipping schedule. A curved, imported facade typically needs several months from approved shop drawings to installation; the exact programme should be built from the glass and shipping lead times.
Can you work with local contractors and site teams?
Yes. We can supply the system, the shop drawings and the installation supervision, and work with a local installer. The key is to define the installation boundary and the inspection points before the facade arrives.
Send the project brief, not just the drawings
Send the architectural drawings, the site photos, the structural information, the performance brief and the site constraints. We will return a feasibility review, an RFI list and a takeoff by system — before you commit to fabrication.